Location
Burnaby, British Columbia
Expertise
Bridges
Share
The Willingdon Avenue Overpass crosses the Burlington Northern rail tracks and two roadways approximately half a kilometre north of the Trans-Canada Highway.
Constructed in 1967, the 75 metre-long, three-span bridge carries six lanes of traffic along an important traffic artery and designated disaster response route. The overpass consists of ten, three-span, continuous pre-stressed concrete I girders, with a continuous concrete deck slab; and a substructure consisting of cast-in-place abutments and two inclined precast column piers, founded on spread footings. Both abutments are seated on fill retained by concrete retaining walls. The inclined pier columns are pinned at either end and provide little or no lateral restraint to the bridge.
Client
City of Burnaby
Project Highlights
The City of Burnaby retained Associated Engineering to complete a seismic evaluation and design of seismic upgrades.The assessment of the bridge identified several seismic vulnerabilities, including insufficient abutment wall strength, inadequate girder seat lengths and shear keys at girder ends, and deficient connections between the precast columns and girders. The seismic retrofit scheme consisted of soil anchors at both abutments to stabilize the abutment retaining walls; concrete shear blocks at the north abutment to prevent transverse sliding of the abutment; shear keys between the precast girders at each abutment; and column restrainers at each girder–column connection.
Following design, Associated Engineering provided contract administration and construction inspection services for the $0.5 million seismic retrofit construction contract.
More Bridges Projects
See all projects
Bridges
Howard’s Pass Access Road Bridge Replacement and Road Improvement
Bridges
Deh Cho Bridge, Quality Management Services
Bridges
Yoho Bridge Concrete Design
Transportation
Coast Meridian Overpass Detailed Inspection
Bridges
Miette Hot Springs Culvert and Bridge Replacement
Bridges
West Main Street Bridge Restoration
Transportation
Whitemud Creek Oxbow Boardwalk
Bridges
170th Street Bridge Over CN Rail Bissell Yard
Infrastructure
Churchill Airport Runway Upgrades
Bridges
Beaverdams Road and Power Canal Bridges
Transportation
BC Earthquake Integrated Asset Management Plan
Bridges
Muskeg River Bridge
Bridges
Lake City Overhead Seismic Retrofit and Structural Rehabilitation
Bridges
Seymour Canyon Suspension Bridge
Bridges