Location
Alberta
Expertise
Energy
Electrical Instrumentation & Controls
Share
The City of Red Deer developed a consultant assignment to complete necessary assessment, panel design, and programming services.
Associated Engineering was awarded the work as a prime consultant.
The City encountered several unanticipated design and construction issues within their larger expansion projects, which affected our assignment and schedule. We have subsequently adjusted almost all aspects of our scope of work to allow for efficient and cost-effective completion of both retrofit changes and the City’s expansion project.
Work has included:
- Update of the 2008 Instrumentation and Controls Master Plan.
- Assessment and design of improvements for 15 major control panels.
- Review and revision of the fibre optic communication network design.
Client
City of Red Deer
Project Highlights
$20 million
Construction Cost
15
Major Control Panels
More Energy Projects
See all projects
Energy
Minoru Aquatic Complex
Energy
Nelson District Energy Feasibility Study
Energy
Process Energy Audits
Building Mechanical
Elijah Smith School Energy Audit
Energy
Solar Feasibility Study for Medicine Hat Reservoirs
Energy
Sylvan Lake Instrumentation & Control Services
Climate Change Adaptation & Mitigation
Nanaimo Reservoir No. 1 and Energy Recovery Facility
Energy
Surrey Civic Centre Plaza
Energy
Gateway Theatre Wastewater Heat Recovery
Energy
Solar Photovoltaic System Installation
Building Mechanical
Residuals Treatment Facility
Electrical Instrumentation & Controls
Solar Photovoltaic System Installation – WTP and Pumphouse
Building Mechanical
Yard Works Facility Emergency Backup Generator
Energy
New Central Library Direct Energy Service Connection and Energy Transfer Station
Building Mechanical