The Johnson-Mariner Connector comprises a 245 m long, four-lane bridge, an integral 100 m long two-lane ramp, 300 m of new road, 700 m of improvements to the Barnet Highway, water main, streetlighting, and provision for pedestrian and bicycle traffic.

The structure provides a grade-separated crossing of the CP Rail mainline and West Coast Express Commuter Rail, and crosses over the environmentally-sensitive Scott Creek flood plain and under BC Hydro power lines.

After extensive evaluation, MoT engaged the design-build team of Peter Kiewit and Sons and Associated Engineering. The team’s design-build concept dealt most effectively with the site’s sensitive geotechnical and environmental conditions, reduced land requirements, and provided the most innovative and aesthetically-pleasing solution.

Map Image
Blue Section

Project Highlights

245m

four-lane bridge

100m

two-lane ramp

300m

new road

700m

improvements

Preloading the north approach and the use of piles for supporting the structure minimized the height of approach fills, reduced long-term settlement concerns, and improved accessibility beneath the elevated roadways. The use of a slender structure reduced the road grades, thereby minimizing the impact on adjacent properties. Despite a relatively heavy superstructure in a high seismic zone, the concrete slab solution proved to be 25% less costly than conventional designs.

Green Section

Careers

A career step in the right direction

We are recognized as one of Canada’s Best Managed Companies for 14 consecutive years but our achievements and reputation are only possible because of our amazing staff. We believe that a supported staff allows them to excel at what they do best, and provide the best possible service to our clients and communities.