The City of Edmonton’s Gold Bar Wastewater Treatment Plant upgrade program continued with a $10 million capital works project.

Construction and commissioning was completed in December, 2004. This project, led by Associated Engineering in collaboration with sub-consultants UMA and Magna IV, included the design and construction of an eleventh 32 ML/d biological nutrient removal (BNR) treatment train. This project also included:

  • A feasibility study for a 40 ML/d membrane based reuse quality water facility
  • Evaluation of a 150 ML/d facility to disinfect secondary treatment bypass flows
  • A new 320 ML/d alum storage and dosing facility
Map Image
Blue Section

Project Highlights

Design of an alum dosing system for phosphorus removal was also performed by Associated Engineering to ensure year-round targets can be met under all foreseeable raw water conditions.

The City of Edmonton has progressively approached full plant conversion to a BNR process throughout the 1990’s, often in studies involving Associated Engineering. A number of reports and trials have been performed to confirm BNR capability and process stability under varying plant and climatic conditions.

LEADERSHIP INSIGHTS

See all insights

Green Section

Careers

A career step in the right direction

We are recognized as one of Canada’s Best Managed Companies for 14 consecutive years but our achievements and reputation are only possible because of our amazing staff. We believe that a supported staff allows them to excel at what they do best, and provide the best possible service to our clients and communities.