The Regional Municipality of Wood Buffalo identified the need for additional residential development within the Hamlet of Fort Chipewyan to accommodate future growth in the community.
Associated Engineering assisted the Municipality with the review of alternative servicing options and costs for the proposed development.
The Hamlet of Fort Chipewyan presented a number of unique geographic and geologic challenges for the design and construction of municipal services. These challenges included:
- The remote location that limits the local availability of construction contractors, equipment and materials.
- Limited access to the area requiring seasonal mobilization of equipment via the winter road from Fort McMurray, barge transport or air cargo.
- Ground conditions consisting of very shallow hard bedrock that requires blasting for installation of underground utilities.
Project Highlights
As a result, development within the Hamlet requires unique engineering consideration, such as: water and sewer mains typically built within the frost zone, a looped water system to enable ongoing circulation, ongoing low flow into the sewer system, above ground utilities, and surface drainage. Our engineering analysis considered these local needs which impact design criteria, construction methods, costs and materials.
To prepare Concept Plans for Residential Little Lake Expansion, the Associated Engineering completed the following tasks:
- Review of existing infrastructure systems to determine available capacity
- Preparation of design criteria
- Development of a number of servicing options considering development scenarios and different levels of service
- Capital and operating costs comparisons.
More Infrastructure Projects
See all projects
Environmental
Phase I Environmental Site Assessment of 10 Housing Units
Water Treatment
Russell Binscarth Water Treatment Plant
Transportation
Granville Bridge Seismic Retrofit and Renewal
Infrastructure
Clayton Reservoir
Transportation
Cold Lake CRISP
Infrastructure
East Brampton Trunk Sanitary Sewer Twinning
Infrastructure
Melville Water Treatment Plant
Transportation
Sutherland Ave Pedestrian Bridge
Buildings
Corix Biomass Energy Centre
Infrastructure
Kluskus Village Domestic Water System Improvements
Building Structures
Bone Yard Operations Centre Office Expansion
Infrastructure
Tsawwassen Mills Mall
Infrastructure
Mosquito Creek Marina Spirit Trail
Environmental
Climate Change Risk Assessment
Hydrotechnical
Medicine Hat Flood Assistance
LEADERSHIP INSIGHTS
See all insights