Location
Slave Lake, Alberta
Expertise
Share
The Slave Lake region was severely affected by wildfires in May 2011 that destroyed a significant portion of the town.
The infrastructure was further deteriorated due to the intensive residential and commercial reconstruction efforts. Associated Engineering was retained to provide consulting services, design, procurement and construction services for the four-year infrastructure recovery efforts, including rehabilitation of:
- 3,100 m of watermain
- 930 m of sanitary sewer
- 810 m of storm sewer
- 120 misc. utility spot repairs
- 8,600 m of walkway
- 3,900 m of curb
- 93,000 m2 of roadway.


Project Highlights
The project had a fixed budget and cost control measures were essential. The project required an effective procurement and phasing strategy to consider homeowner access, transportation routes disruption, and ongoing utility services. The project team selected a construction management approach, somewhat unique for urban rehabilitation, to enable more flexibility and collaboration and successfully deliver this project.
More Infrastructure Projects
See all projects

Strategic Advisory Services
Peterborough Streetlight Condition Assessment

Infrastructure
Heavy Rainfall Event Disaster Recovery

Infrastructure
Tsawwassen Mills Mall

Building Structures
Bone Yard Operations Centre Office Expansion

Transportation
Moody Street Overpass

Transportation
Broadway Street Improvements

Infrastructure
Buffalo Creek Culvert Replacement

Water
Jericho Reservoir

Strategic Advisory Services
East Side Pump Station Asset Management Plan

Bridges
Haisla Bridge Replacement

Infrastructure
West Edmonton Sanitary Sewer Tunnel W12

Infrastructure
Yoho Bridge Concrete Design

Infrastructure
Burnaby Lake Rowing Club Pavilion Floating Dock

Buildings
North Wall Sewage Treatment Plant and Main Lift Station Upgrade

Land Development
Blackwolf Community Development
LEADERSHIP INSIGHTS
See all insights