Location
Fort McMurray, Alberta
Expertise
Transportation
Bridges
Remote & Resource Bridges
Share
Canadian Natural Resources Ltd. (CNRL) required a road and bridge over the McKay River, 500 kilometres north of Edmonton, to provide access to future mining operations in the region.
In addition to highway traffic, the bridge needed to carry 840 tonne, owner-specified, overload vehicles, among the heaviest vehicles to travel on Alberta’s roads. The project comprised a new 262 metre, five span, two‑lane bridge and 9 kilometres of roads.
CNRL retained the design-build team of Kiewit Management Company, Brybil (an affiliate of Associated Engineering), AMEC Earth and Environmental and AMEC Infrastructure. Associated Engineering provided overall design, project management, detailed design of the bridge, construction services, and coordination of work with the Department of Fisheries and Oceans and Alberta Environmental Protection.
Client
Canadian Natural Resources Ltd.
Project Highlights
840T
Weight
9KM
Roads
This project had an accelerated schedule, progressing from design through to substantial completion in just ten months. Associated Engineering completed the bridge design over a period of three months, while continually providing critical information. This was done by developing a quality control program that facilitated the partial release of design information prior to actual design completion. The program facilitated the ordering of all materials prior to issuing construction drawings. Associated Engineering provided on site engineering services through all critical stages to ensure that the project proceeded on schedule.
People on this project
More Transportation Projects
See all projects
Transportation
Calgary Airport Runway and Tunnel
Transportation
Ray Gibbon Drive Twinning
Transportation
Coast Meridian Overpass Detailed Inspection
Transportation
Granville Bridge Seismic Retrofit and Renewal
Transportation
Ice Engineering and Ice Safety for Tibbitt-Contwoyto Winter Road
Transportation
Freegold Road Functional Plan
Roads
Johnson-Mariner Way Connector
Transportation
Medicine Hat Boardwalk Replacements
Pedestrian Bridges
Dayton Street Pedestrian and Cycling Overpass
Transportation
Cowichan Valley Trail Bridges Condition Inspection and Load Rating
Transportation
BC Earthquake Integrated Asset Management Plan
Transportation
Haisla Bridge Replacement
Transportation
Highway 17 at County Road 508 Interchange
Infrastructure
Churchill Airport Runway Upgrades
Transportation
Still Creek Pedestrian Bridge Replacement
LEADERSHIP INSIGHTS
See all insights