Two weeks after the June 2013 flood, Sunnyside’s stormwater system received a rainfall that couldn’t be discharged to the Bow River, as most of the outfall gates were closed to protect the community.
The City of Calgary worked with Associated Engineering to examine this unusual flooding sequence and propose resiliency upgrades.
When historical analysis showed that high-intensity rainfall and high river levels had been independent, the team suggested an innovative dual level of service approach, substantially reducing the cost of improvements. A first for the City, this approach sets a precedent for other floodplain communities seeking cost-effective stormwater management solutions.
Client
The City of Calgary
Project Highlights
People on this project
More Infrastructure Projects
See all projects
Infrastructure
Mosquito Creek Marina Spirit Trail
Transportation
Agassiz-Rosedale Bridge – Renewal Options Analysis and Preliminary Rehabilitation Design
Infrastructure
Gold Bar Wastewater Treatment Plant
Transportation
Vancouver International Airport Rainwater Harvesting
Bridges
Moody Street Overpass
Infrastructure
West Edmonton Sanitary Sewer Tunnel W12
Environmental
Drinking Water System Improvements in Quaaout Community
Water Treatment
Russell Binscarth Water Treatment Plant
Computational Fluid Dynamics Analysis
E.L. Smith Water Treatment Plant Upgrade
Environmental
Port of Vancouver – Climate Change Adaptation
Infrastructure
Provincial Disaster Assistance Program
Infrastructure
Wildfire Infrastructure Rehabilitation Program
Energy
New Central Library Direct Energy Service Connection and Energy Transfer Station
Transportation
Ironworkers Memorial Second Narrows Bridge Fatigue Study
Transportation
Bellevue Creek Bridge
LEADERSHIP INSIGHTS
See all insights