Location
Calgary, Alberta
Expertise
Infrastructure
Urban Drainage
Share
Two weeks after the June 2013 flood, Sunnyside’s stormwater system received a rainfall that couldn’t be discharged to the Bow River, as most of the outfall gates were closed to protect the community.
The City of Calgary worked with Associated Engineering to examine this unusual flooding sequence and propose resiliency upgrades.
When historical analysis showed that high-intensity rainfall and high river levels had been independent, the team suggested an innovative dual level of service approach, substantially reducing the cost of improvements. A first for the City, this approach sets a precedent for other floodplain communities seeking cost-effective stormwater management solutions.
Client
The City of Calgary
Project Highlights
People on this project
More Infrastructure Projects
See all projects
Parks & Recreation
Pexsisen Elementary School
Infrastructure
Irrigation Sustainability and Water Balance Seepage Assessment Study
Infrastructure
Kennedale Snow Storage Site Development
Infrastructure
Tsawwassen Mills Mall
Infrastructure
Ice Engineering, Safety Services, and Road Management Plan
Streetscaping
Vanalman Avenue Upgrades
Transportation
Highway 17 at County Road 508 Interchange
Pedestrian Bridges
Dayton Street Pedestrian and Cycling Overpass
Transportation
Bellevue Creek Bridge
Infrastructure
Minnedosa Community Housing
Building Mechanical
South Arm District Energy Utility Phase 1 Technical Feasibility Study
Active Transportation
Highway 1 at Mountain Highway Interchange
Infrastructure
North Interceptor Sanitary Trunk
Infrastructure
Provincial Disaster Assistance Program
Transportation
Coast Meridian Overpass
LEADERSHIP INSIGHTS
See all insights