Location
Fort Providence, NWT
Expertise
Bridges
Infrastructure
Quality Management
Share
The Deh Cho Bridge is a new 1.1 km steel truss and cable stayed bridge across the Mackenzie River near Fort Providence, Northwest Territories (NWT) providing a year-round transportation link from Yellowknife to other parts of the NWT and to the rest of Canada. It replaced the location’s existing ferry operations and ice crossing.
Associated Engineering, with its consulting partners, provided quality management services to monitor the activities of the contractor, subcontractors, suppliers, and consultants, to review the quality and completeness of their documents and records, and to assess the effectiveness of actions taken to resolve quality issues, including the identification, tracking, correction, and verification of nonconformities.
Because of the project’s remote location, its extreme weather conditions, and the short yearly seasonal construction periods, it was essential to minimize quality issues that would require repair in the field or replacement of components (which often necessitated long delivery times) by encouraging adaptation of construction methodologies, shop prefabrication processes, and improvements in the transportation and receipt of materials, resources, and personnel. A rigorous quality assurance, quality audit, and quality monitoring program was undertaken of the on and off-site fabrication activities and of the contractor’s field assembly and installation works. These efforts contributed greatly towards ensuring faster construction speed and savings.
Completed and officially opened to great local and territorial celebration on November 30, 2012, the bridge has been a valuable asset to the NWT providing an efficient, year-round, cost effective transportation link for trucking, businesses, industries, and residents.


Project Highlights
More Bridges Projects
See all projects

Transportation
Medicine Hat Boardwalk Replacements

Bridges
Yoho Bridge Concrete Design

Bridges
Fifth Bridge Replacement

Transportation
Kitsault Mine Access Road and Bridge Assessments

Bridges
Seymour Canyon Suspension Bridge

Transportation
Kapuskasing River Bridge

Transportation
Glenmore Dam Utility Relocation

Environmental
Deh Cho Bridge, Environmental Services

Bridges
Frank Channel and Kakisa River Bridge Assessment

Bridges
170th Street Bridge Over CN Rail Bissell Yard

Transportation
Casino Mine Access Road

Transportation
Overlea Blvd. Bridge Rehabilitation

Active Transportation
Highway 1 at Mountain Highway Interchange

Transportation
184 Street and Yellowhead Trail Interchange

Bridges
Miette Hot Springs Culvert and Bridge Replacement
LEADERSHIP INSIGHTS
See all insights